Park & Ride waiting room – High Wycombe

single ply EPDM waterproofing system roof

Project required erection of temporary fencing and scaffold to protect public and operatives. Removal of existing waterproofing and defective ply decking.

Installation of new 18mm ply and RubberBond fleeceback single ply EPDM waterproofing system. Work completed one week ahead of schedule allowing facility to re-open earlier.